The full set of engineering lines for Kenyan coconut shell activated carbon equipment has been installed, and coconut shell activated carbon has a high popularity worldwide. Our company received an order in mid 2022 and officially started construction by the end of the year. As of April 2023, the full set of engineering produced by our company has been installed.
Figures 1 and 2 show the layout of the entire production line's factory building
The image below shows the equipment of the activated carbon activation furnace
The diagram below shows the construction site of the carbonization furnace flue gas incinerator. The device mainly incinerates the flue gas completely and uses excess heat to burn the cylinder, ultimately completing the carbonization of coconut shells.
At the lifting site of the rotary activation furnace, a crane is used to install the activation furnace equipment on a pre made base. The purpose of doing so is to make the operation of the activation furnace equipment more stable.
After the complete system installation is completed, our technical personnel and Kenyan technical personnel will take a group photo as a souvenir.
This section covers scenarios of thermal energy recycling such as waste heat boiler systems and incinerator systems.
The coconut shell activated carbon production line covers an area of approximately 2000m ², So taking photos is extremely difficult and can only provide some perspective for everyone. If you are interested in investing in activated carbon production equipment, please come to our company for inspection and visit.